- Sewerage infrastructure
- Drainage infrastructure
- Potable water treatment infrastructure
- Wastewater purification and regeneration infrastructure projects
- Infrastructure projects for reusing regenerated water
- Capture and distribution projects for irrigation water
- Potable water supply master plans
- Sewerage master plans
- Drainage master plans
Sewerage connection from Sant Pere Pescador and L'Armentera in the L'Escala WWTP
YEAR:
2009
DESCRIPTION:
Complete design of the sewerage system connection from Sant Pere Pescador and L'Armentera in the L'Escala wastewater treatment plant (WWTP). To complete this objective, 16 km of pipeline and 7 pumping stations were installed.
Developer: Consorci de la Costa Brava (Costa Brava Consortium)
2009
DESCRIPTION:
Complete design of the sewerage system connection from Sant Pere Pescador and L'Armentera in the L'Escala wastewater treatment plant (WWTP). To complete this objective, 16 km of pipeline and 7 pumping stations were installed.
Developer: Consorci de la Costa Brava (Costa Brava Consortium)
Master plan for basic sewerage infrastructure in the Girona urban area
YEAR:
2005
DESCRIPTION:
Planning document (definitions, assessments and scheduling) of the necessary basic sewerage infrastructure, taking into account both the current shortcomings (as measured) and the estimated urban growth as defined in the urban plans of the different municipalities that make up the Girona urban area. (10 Municipalities)
Developer: area municipalities and the Agència Catalana de l'Aigua (Catalan Water Agency)
2005
DESCRIPTION:
Planning document (definitions, assessments and scheduling) of the necessary basic sewerage infrastructure, taking into account both the current shortcomings (as measured) and the estimated urban growth as defined in the urban plans of the different municipalities that make up the Girona urban area. (10 Municipalities)
Developer: area municipalities and the Agència Catalana de l'Aigua (Catalan Water Agency)
Expansion of the Figueres potable water treatment plant (Girona)
YEAR:
2003
DESCRIPTION:
Complete design and construction supervision for the Figueres water treatment plant expansion. System designed to treat a total of 920 m3/h. Work in progress during 2006 and 2007.
Developer: Fisersa
2003
DESCRIPTION:
Complete design and construction supervision for the Figueres water treatment plant expansion. System designed to treat a total of 920 m3/h. Work in progress during 2006 and 2007.
Developer: Fisersa